Modernization of Power Plant Merkenich, Cologne, Germany
Modernization of power plant Merkenich
Life-time extension and efficiency improvement of lignite fired cogeneration CFB plant. The following services were executed by STEAG Energy Services (SES): Project Management, main design, detailed design, permit engineering, preparation of lot tender documents, tender evaluation, contract negotiations, interface coordination, design review.
Project facts
Installed capacity | 85 MWel, 76 MWth |
Technology | Circulating Fluidized Bed (CFB) |
Fuel | lignite |
Customer | Rhein Energie AG |